A Medium Installation is defined as 2-4 Cases and/or 15-20 Objects.
24 Weeks (6 Months) Prior
Exhibition organizer has:
- Completed the exhibition checklist (left-hand side of the template is completed, including display/opening information)
- Identified any imaging needs
Library contact has:
- Pulled and flagged collection items so that they correspond with the exhibition checklist
- Determined who needs to be included in the conservation review meeting (e.g., collection manager, curator, registrar, format-specific conservator, preparator, imaging staff, AV coordinator, digital project coordinator, designer)
- Scheduled appointment for conservation review of the exhibition checklist
- Identified any items that are beyond the scope of the Weissman Preservation Center (such as objects or paintings; i.e., NOT a book, paper, or photographic format) and thus require treatment by a contract conservator
11 Weeks Prior
Library contact completes the following:
- Conservation review with pre-determined group is completed
- Exhibition Checklist is updated (right-hand side of the template, includes condition issues, treatment estimate, treatment location, and cradle and support needs)
- General due date for onsite and offsite treatment is determined. Treatment should be completed before imaging and cradle and support-making; treatment due date should reflect imaging and cradle and support-making time requirements
- Transfer of any materials being treated offsite is scheduled (within the week after the conservation review)
- All work associated with the exhibition is scheduled based on the exhibition checklist
10 Weeks Prior
Library contact completes the following:
- Transfer of materials being treated offsite occurs
- Offsite treatments begin, prioritizing those items with imaging orders
- Onsite treatments begin, prioritizing items with imaging orders and those treatments that are estimated to be more complicated and time-consuming
9 Weeks Prior
Library contact facilitates the following:
- Mat measurements for any framed works are taken and frame sizes are confirmed
- Cradle- and support-making begins, focusing on completed onsite treatments
- Offsite and onsite treatments continue
8 Weeks (2 Months) Prior
Library contact facilitates the following:
- Mats are ordered or cut in house
- Completed treatments are sent to Imaging
5 Weeks Prior
Library contact facilitates the following:
- Framing begins
- Items return from Imaging
3 Weeks Prior
Library contact facilitates the following:
- Framing is completed
- Cradles and supports are completed
2 Weeks Prior
Exhibition team finalized content for labels
Library contact facilitates label printing, mounting, and cutting
1 Week Prior
Library contact facilitates deinstallation
Exhibition team installs the exhibition space